Foundation work complete at 42-44 Crescent Street

We last checked in at 42-44 Crescent Street in January when the project had restarted after a long hiatus.1 We stopped by last week and took a look inside the project, and foundation work has been completed, as seen in the photo below. Permits, approved on Nov. 17, 2017, call for 12,495 square feet of […]
Continue reading…

 

A new rendering appears at 42-44 Crescent Street as work restarts

The last time we stopped by¬†42-44 Crescent Street was in July of 2017, when progress has stalled on the site.1 Recently, a new rendering appeared, calling for a winter 2018 delivery, and work has restarted on site, as seen in the photo below. Steel beams have been installed, rising well above the construction fence. Permits, […]
Continue reading…