There are two hurdles to the completion of 26-20 Jackson Avenue:1 The roofdeck and the ground floor. Construction crews are working on both. We’ve seen crews laying down wood paneling on the top floor, and just recently, we’ve seen workers tearing out the old industrial windows on the ground floor to make way for more residential counterparts. Crews also are putting up sheet rock on the interior of the commercial space.
According to the filings with the Department of Buildings, there will be nine residential units (9,130 square feet) and one commercial space (1,692 square feet) in the building.2 The original delivery date was Summer, 2014.
Pingback: Thursday Links | Brownstoner Queens