Outside facade work mostly complete at 22-22 Jackson Avenue

The last time we stopped by 22-22 Jackson Avenue was in April when we noticed the building had just topped and and outside facade work was underway.1 When we stopped by last week, we saw that facade work is mostly done, with windows installed in over 95 percent of the building. It seems that 22-22 Jackson will likely finish by the end of the summer, which is on target with its initial goal.

According to BuzzBuzzHome,2 the building will have 118,563 square feet of residential space in 82 units and 5,723 square feet of retail space. Amenities include bike storage, a library, pool, gym, lounge, communal rooftop rec space, enclosed parking and private terraces.