The last time we checked in at 21-22 45th Road a/k/a 21-30 45th Road a/k/a 21-20 45th Road was in August, when construction had reached the halfway point.1 When we stopped by last week, we saw that construction is now at the third of four floors, as seen in the photo below. Signage calls for a December 2018 delivery.
There have been many, many variations of permits that have been filed for this lot, but New York YIMBY was the first to note that the project will eventually turn into a six-building, 36-unit residential development.2

A view of 21-22 45th Road

Rendering for 21-30 45th Road